OREGON — Oregon City Council voted 6-1 on Monday night to shrink the data-center land deal, letting developer Will Turner’s company, Capacity LLC, buy about 63 acres for $4.13 million — or walk away by 5 p.m. July 31, 2027, and get most of its deposit back. The Lake Erie Inquiry reported the vote came 13 days after voters banned large data centers in the city.

For Clay High School, the smaller deal carries a direct cost. Turner said $500,000 that Capacity had planned for the school’s trades program is now off the table, along with money for electrical-trades training for Toledo Public Schools. “Nobody pays like data centers do,” Turner said. He said a replacement project bringing in $2 million in revenue would not compare with what the data center would have paid.

The new deal replaces a much larger one. The original agreement covered more than 168 acres and, by February, would have cost $18 million with four more lots included. The revised agreement covers 62.9 acres at about $66,000 an acre. Walters said the city had paid slightly more than $3 million for the 62.9 acres it is now selling for $4.13 million.

The city owns one of the four parcels in the deal; the Oregon Economic Development Foundation owns the other three. Turner said the buyer intends to sell the land after closing, and the agreement’s stated purpose has changed from “for eventual use as a data center” to “for eventual industrial use.” There was no word at the meeting on whether Vantage Data Centers, the intended user of the original project, is still involved.

Hornyak moved to approve the revised agreement, and Andrus seconded it. Drake, Gibbs, Pollauf and Walendzak also voted yes. Ackerman cast the only no vote, saying the deal was moving too fast — the city found out about it Friday, he said — and questioning the time crunch Turner cited. The measure was passed as an emergency, so it takes effect when the mayor signs it. City Law Director Melissa Fifer said timing was an issue because the existing contract runs out at the end of the month.

The vote follows the Nov. 3 election, when voters approved Issue 25, banning data centers larger than 25 megawatts. Two days later, Vantage said the project would not move forward as proposed. Under draft terms discussed in September, Vantage would have paid $20 million to the city and schools and about $14 million a year in lieu of property taxes once the data center was built. “We missed out on the goose that laid the golden egg,” Gibbs said Monday.

The smaller deal does not solve Oregon’s budget problem. Hornyak said she expects the city to ask voters for a tax increase next year, and it is not yet known whether coming cuts will avoid layoffs. Walendzak said a week earlier that “multiple millions” have to be cut from the budget; the city’s general fund spent $28.5 million and took in $25.6 million in 2024, according to audited figures. The Finance Committee will discuss the budget Nov. 23 from 5 to 7 p.m. ToledoBuzz reported last week on the cuts Oregon faces after voters killed the data center.

Turner said there is no named project yet for the land, but industries are growing in energy and defense, including transformer parts, generators and parts for the Navy. The deposit under the revised deal drops to $40,000, from $100,000.

Source: The Lake Erie Inquiry, “Oregon council gives data-center developer a smaller land deal,” published Nov. 17, 2026.

Photo: Rsparks3, via Wikimedia Commons (CC0). The photo shows the roof of a data center, with cooling towers and backup generators.

Top Stories

The Daily Fresh